Project information
Saigon Gia Dinh Electric Joint Stock Company is executing a project to supply 60MVA of electricity to Samsung Company in the high-tech zone of District 9. As an EPC Contractor, EHCMC started the project on December 10, 2015, conducted acceptance testing and COD on December 22, 2016. The construction time lasted in 72 days – a new record EHCMC and its workers achieved, meeting the expectation of the Investor.
Completion Date | 2016 |
---|---|
Contractor | Saigon Gia Dinh Electric Joint Stock Company |
Construction Location | District 9, Ho Chi Minh City |